Wire Rope Inspection: When to Retire a Rope

Wire rope announces its retirement in advance — broken wires, diameter loss, and deformation all appear before failure. The inspector's job is knowing where to look and what counts. Here are the criteria from ASME B30 practice, in field language.

The Two Inspection Levels

Frequent (each shift/use, by the operator): visual scan of the working length for obvious damage, kinks, and broken wires. Periodic (documented, by a designated inspector, at intervals set by service severity): full-length inspection with diameter measurements, records kept per rope.

Broken Wire Limits

Application Removal criteria
Running ropes (hoists, cranes) 6 randomly distributed broken wires in one lay, or 3 in one strand in one lay
Slings 10 in one lay, or 5 in one strand in one lay
Rotation-resistant ropes 2 in 6×d, or 4 in 30×d
Any valley breaks 1 valley break = remove
At end terminations 2 broken wires = remove or re-terminate

Flex the rope over a bar to expose hidden breaks; run a cloth to catch fishhooks.

Diameter & Deformation

Measure across the crowns with a caliper and compare to nominal: reduction to 1/32" under nominal (small ropes) or per the crane manufacturer's limit means retirement — diameter loss signals core failure or internal wear. Retire immediately for kinks (birdcages, popped cores, doglegs), crushing, flattening over drum crossovers, and any heat damage: arc strikes and torch contact make rope scrap on the spot.

Corrosion & Lubrication

Pitting corrosion — especially internal, revealed by opening the lay slightly — is retirement; surface rust with intact wires calls for cleaning and re-lubrication. Field lube should penetrate (thin, then film), applied at a bend where strands open. A dry rope wears from the inside invisibly; lubrication is inspection's partner, not an afterthought.

Records That Hold Up

Per-rope file: installation date, construction and cert, periodic inspection dates, measurements, and findings. When an incident review asks for it, this file is what stands between a program and a citation.